Pay-When-Paid Clauses: What to Accept and What to Push Back On
A GC says he'll pay you when he gets paid. Here is how to read the clause, tell pay-when-paid from pay-if-paid, and decide what to accept, push back on and protect.
By the MagicBuild team ·
If a GC says "we'll pay you when we get paid," do I still get paid if the owner never pays?
Often yes, but it depends on the exact words in your contract. Most courts read a plain pay-when-paid clause as a timing provision, so the GC still owes you within a reasonable time even if the owner never funds the draw (Corpay).
The catch is that "a reasonable time" is not a date. You did the work, you fronted the materials and payroll, and you have nothing to point to. If the contract goes further and says the owner's payment is a condition of your payment, you may be carrying the owner's credit risk, and that is a different deal.
Before you answer the GC, do three things:
- Find the sentence in the subcontract that mentions payment from the owner.
- Ask who the owner is, whether there is a lender, and when draws are scheduled.
- Ask when the GC expects to be paid for your scope specifically.
This is general information, not legal advice. For a big contract, a short review by a construction attorney is cheap next to a lost invoice.
What's the difference between pay-when-paid and pay-if-paid, and how do I spot which one is in my contract?
Pay-when-paid is about timing, while pay-if-paid makes the owner's payment to the GC a condition of the GC's duty to pay you, where it is enforceable and properly drafted (Corpay). Look for the words "condition precedent," because that is where the risk moves onto you.
Here is how common wording usually reads:
| Clause wording | What it usually means | Your risk |
|---|---|---|
| "Sub will be paid within a reasonable time after GC receives payment" | Pay-when-paid, timing only | Delay with no firm date |
| "Payment by the owner is a condition precedent to GC's obligation to pay" | Pay-if-paid | You may not be paid if the owner doesn't pay |
| "Only to the extent GC receives payment from the owner" | Leans pay-if-paid | Partial or no payment |
| "Net 30 from invoice, whether or not the owner has paid" | Fixed deadline | Lowest risk of the four |
Other red flags are "if and only if," "sole source of payment," and any line saying the sub assumes the risk of owner nonpayment. Highlight every sentence that ties your money to the owner, then read the clause on retainage and final payment too, since they often repeat the same condition.
Is a pay-if-paid clause even legal in my state?
It depends on your state, and nobody can tell you what is enforceable where you work without checking your local law. Enforceability varies significantly, with some states voiding or limiting pay-if-paid clauses by statute and others requiring explicit condition-precedent language (Corpay).
Texas is one example of the "clear language" approach. Texas law treats owner payment as a condition precedent only if the subcontract uses stronger language that clearly shifts the owner's credit risk to the subcontractor (Fasthoff Law Firm). Your state may be stricter, looser, or silent.
To find out, call your state's contractor registration office or a local construction attorney and ask one question: "Is a pay-if-paid clause enforceable against a subcontractor here, and what wording does it take?" If you sign the same kind of subcontract often, that one answer is worth having in your files.
What payment terms should I ask for instead: Net 30, a payment deadline, or progress billing?
Ask for a fixed payment deadline counted from your invoice date, such as Net 30, instead of a date tied to the owner's payment. Net 30 is not an unusual ask, since almost half of construction businesses give customers 30 days or more to pay, and only 11% regularly charge interest or fees for late payments (Levelset).
You will not win every point with a GC who has the leverage, so rank your asks:
- A hard outside date. Something like "paid within 30 days of invoice, whether or not the owner has paid." If the GC won't drop the clause, this is the compromise to push for.
- Progress billing. Invoice monthly or at milestones instead of one bill at the end, so you never carry the whole job.
- A retainage limit. Ask for a cap and for release when your scope is accepted, not when the whole project closes. Say a $12,000 rough-in has 10% retainage held until the project closes, which means $1,200 stays with the GC long after your crew has left.
- Late fees or interest. Few contractors charge them, but asking costs nothing and gives you something to trade.
- Money up front for materials. A deposit or a materials draw keeps you from being the bank. If you take deposits, spell out the amount and trigger in the contract.
If you can only win one, take the outside date.
Do I lose my lien rights if I sign a pay-when-paid contract?
Not automatically. Neither a pay-when-paid nor a pay-if-paid clause automatically waives lien rights, but they can affect the timeline and make notice deadlines more critical (Truss Payments).
The danger is waiting. Lien and notice deadlines run on their own clock, not on the GC's payment schedule, so "he's still waiting on the owner" can quietly use up your window. Lien rules differ by state, so confirm yours with your state's contractor registration office or a construction attorney.
A practical routine that works under almost any rule set:
- On day one, find out whether your state requires a preliminary or pre-lien notice, and send it on time.
- Write down the first day you worked and the last day you worked.
- Read every lien waiver before you sign. A waiver can give up rights, and some are meant to be signed only after the check clears.
- Put the owner's name and the property address in your files from the start.
Can I stop work if the GC isn't paying me, or will that put me in breach?
Only if your contract gives you that right, so check for a stop-work or suspension clause before you pull your crew. Without one, the GC can argue that walking off was a breach, and now you are the one in trouble.
If the clause is missing, ask to add one. Plain language is fine: "If an undisputed invoice is more than 10 days past due, Sub may suspend work after written notice, and the schedule extends day for day." Also ask for the right to demobilize and come back without penalty.
If you have the right, use it carefully:
- Send written notice by email and by a trackable method, and keep copies.
- Name the invoice, the amount and the date it was due.
- Give the deadline stated in the contract, not one you made up.
- Keep doing any safety work you are required to do.
Some states give subs extra rights here, and they vary, so ask a construction attorney before you stop on a large unpaid balance.
How do I protect my cash flow when I'm stuck with pay-when-paid terms, and when is it OK to accept it?
Price the wait, bill early, document everything, and accept pay-when-paid only when the GC has a record of paying you on time. Pay-when-paid is a GC tool for managing cash flow, but it creates significant cash flow problems for smaller subcontractors (Truss Payments).
What to do on a job you have already accepted:
- Invoice the day work is accepted. Use a clean free invoice template with the job, scope and due date on it.
- Keep paper. Daily logs, dated photos, signed change orders and receipts for every material purchase.
- Stage the work. Don't start phase two until phase one is paid or a firm date is in writing.
- Match your suppliers to your terms. Ask for 30-day supplier terms so your bills don't come due before your money does.
- Price the float. Suppose you front $8,000 in materials and wait 60 days. If a credit line or supplier account charges you for that, put the cost in the bid. The free job cost calculator helps you see it.
Here is a quick way to decide on a new job:
| Situation | Accept | Push back |
|---|---|---|
| Clause wording | Timing only, reasonable time | Condition precedent, no outside date |
| GC history | Has paid you on time before | New to you or slow with others |
| Job size | Small next to your cash | Big enough to strain payroll |
| Retainage | Low, released at your scope | Held until the entire project closes |
| Stop-work right | Included | Missing |
If a job lands in the right column on two or more rows, walk away or reprice it.
Software won't change a contract, but it keeps the paper trail honest. In MagicBuild, invoices can be paid online, receipts are filed to the job, and you can see job profit, so you know early when a slow payer is eating your margin. You can read what MagicBuild does for the details.
Try MagicBuild free for 14 days, or start with one of the free tools above. It costs $69 a month after the trial, and your crew and clients don't cost a seat.
Sources
- Pay When Paid vs Pay If Paid (Corpay) · corpay.com
- Pay-When-Paid and Pay-If-Paid Clauses in Texas (Fasthoff Law Firm) · fasthofflawfirm.com
- Pay When Paid Clauses in Construction Contracts (Truss Payments) · trusspayments.com
- Contractor Payment Terms (Levelset) · levelset.com