Did I Undercharge on This Job? How to Check Before the Next Bid

Not sure you made money on the job you just finished? Run a 15-minute check on real hours, real materials and what's left, then price the next bid with a rule you can trust.

By the MagicBuild team ·

How do I know if I undercharged on a job?

You undercharged if what's left after materials, labor and your share of overhead is less than you needed to pay yourself and keep the business running. The simplest test is whether the job paid you more per hour than you would accept from an employer, after every cost.

Run this check within a week of finishing, while receipts and memory are still fresh. It takes about 15 minutes:

  • Write down the total you were paid, including change orders.
  • Add up the real hours for everyone on the job, from texts, your calendar or timesheets. Count drive time, supply runs and walkthroughs.
  • Add up real materials from receipts, not from your estimate.
  • Add the extras: fuel, dump fees, rentals and small stuff.
  • Subtract all costs from the price, then divide what's left by total hours.
  • Compare that number to the hourly figure you need after overhead.

If you want the math done for you, the free job cost calculator walks through the same steps. Other warning signs: the job took far longer than you figured, or you're busy all the time and still short at the end of the month.

How do I figure out what I actually made per hour on a job?

Divide the money left after all job costs by the total hours worked by everyone, then subtract your overhead per hour to see the real number. Most owners stop at the first step and feel better than they should.

For example, say a bathroom tile job was priced at $4,800 and the numbers came out like this:

Example lineAmount
Price paid$4,800
Actual materials$1,350
Fuel, dump fee, extra supply runs$240
Left after job costs$3,210
Total hours, including drive and shopping62
Left per hourabout $52
Overhead per hour (say)$30
Left per hour after overheadabout $22

Overhead is everything you pay whether or not you have a job today: insurance, truck, tools, phone, software, your accountant. If your overhead is $3,600 a month and you work 120billable hours a month, that is $30 on every hour. So if you need $40 an hour to pay yourself, this job came up short by about $18 an hour, or roughly $1,100 over 62 hours.

Getting real hours is the hard part. If your crew checks in and out on a phone, you stop guessing. The crew app in MagicBuild does check-in and check-out, files receipts to the job and shows job profit, so this check is mostly already done when the job closes.

What costs do I forget to count when I look back at a job?

The usual misses are small materials, fuel, extra supply house trips, dump fees, rentals, unpaid drive and shopping time, and callbacks. Housecall Pro warns that missing even one line item can leave you underpricing your services (Housecall Pro).

Go back through the job with this list:

  • Fasteners, caulk, tape, blades, sandpaper, plastic and other small materials that never made it onto the estimate.
  • Fuel and truck wear for every trip, not just the first one.
  • The second and third run to the supply house for the thing you forgot or the thing that was wrong.
  • Dump fees, disposal and cleanup time.
  • Tool or equipment rental.
  • Time spent on the phone, texting the customer and writing the estimate.
  • Fixing something after you left.

The fix is to put these on the next quote on purpose, either as a small-materials line or built into your hourly rate, so you never eat them quietly.

What's the difference between markup and margin, and which one should I use?

Markup is the percent you add on top of your cost, and margin is the percent of the final price that you keep. Use markup to build the price and check margin to see what you actually keep.

The two numbers are never equal, and that's where owners get burned. If a job costs you $1,000 and you add 50% markup, the price is $1,500 and your margin is only about 33%. To reach a 50% margin you need a 100% markup.

Example markup on a $1,000 costPriceMargin you keep
20%$1,200about 17%
30%$1,300about 23%
50%$1,500about 33%
70%$1,700about 41%

If you know the margin you want, divide your cost by one minus that margin. For example, if you want a 30% margin on a $1,000 cost, divide $1,000 by 0.70 and quote about $1,430.

How much markup should I put on materials and labor?

There is no single right number, but if you want an outside reference, Housecall Pro says a good markup usually falls between 30% and 70%, depending on your trade, overhead and business goals (Housecall Pro).

Pick yours by working backward from what the business needs, not from what feels polite. Don't double count: if your hourly labor rate already includes overhead, the markup only has to cover profit and risk. Whether you mark up materials, labor or both matters less than doing it the same way on every bid.

How do I fix my pricing on the next bid without losing the job?

Price from real hours, real materials and overhead, then add a markup you set on purpose, and show the customer clear line items and choices instead of a lower number.

Here is the order:

  1. Look at your last three similar jobs and use their real hours, plus a cushion for what usually goes wrong.
  2. Multiply hours by a labor rate that covers wages and overhead per hour.
  3. Add materials at what you pay, plus a line for small materials, fuel and trips.
  4. Add your markup.
  5. Check the per-hour and margin numbers against your target before you send it.

Say a fence job has $1,200 in materials and 16 labor hours. If your labor and overhead rate is $70 an hour, labor comes to $1,120 and your costs total $2,320. If you add a 25% markup, you quote $2,900.

To keep the bid, itemize so the customer sees what they're buying, and offer a smaller scope or a different material instead of cutting your margin. There is no good data on exactly how much a price increase changes your win rate, so track your own: raise prices on your next five bids and note how many you win.

What do I do if I already gave the customer a price and I'm losing money?

Finish the job, stop the leak now, and only ask for more money for real scope changes. If the extra work is something the customer asked for or something you couldn't have seen, write it up as a change order before you do it.

If the loss is just your own underbid, you usually absorb it and use it to fix the next quote. What you can change after agreeing on a price depends on your contract and your state, so read your contract first and ask your state's contractor registration office if you're unsure.

Should I use a pricing calculator or a price book for my bids?

Use a calculator to set your rate and check a bid, and a price book to keep repeat services consistent, but feed both your own real numbers. Neither one fixes bad inputs.

Jobber's free service price calculator asks for your overhead, working hours each month and hours the job will take, then works out a price (Jobber). Housecall Pro says each industry in its app comes with a Default Price Book, a pre-loaded set of common services and homeowner-friendly descriptions (Housecall Pro). Treat pre-loaded prices as a starting point and compare them to your own actual hours.

MethodBest forWatch out for
Gut feelNothing, once you have job historyMissing costs and hours
Price calculatorSetting your rate, checking a one-off bidWrong overhead or hours going in
Price bookRepeat services you do oftenPrices that don't match your costs
Review after each jobLearning your real hours and marginSkipping it when you're busy

The review after every job is what makes the other methods accurate.

Want to see your job profit without the spreadsheet?

If you'd rather not dig through receipts and texts, try MagicBuild free for 14 days. It costs $69 a month after that, and your crew and clients don't take up a seat.

You can also start with the free job cost calculator or start a free trial.

Sources

  1. How to Calculate Markup and Margin for Home Service Jobs · housecallpro.com
  2. How to Use Price Book by Housecall Pro | Housecall Pro Help Center · help.housecallpro.com
  3. Service Pricing Strategies: 12 Proven Models to Maximize Profit · housecallpro.com
  4. Free Service Price Calculator | Jobber · getjobber.com